The Challenge
Dublin’s Damastown Industrial Park was home to a new pharmaceutical production facility one requiring intricate electrical system fit-outs. The Irish MEP contractor needed a partner to digitally coordinate the project while adhering to strict compliance standards. But the real challenge wasn’t the complexity of the electrical design alone it was the coordination chaos that surrounded it.
- Models from other subcontractors were often outdated or missing.
- Unanticipated site modifications were not documented.
- Producing coordinated construction drawings became increasingly difficult as phase-based model inconsistencies surfaced.
Client’s Initial Hurdles
Before Desapex stepped in, the MEP contractor was grappling with:
- Irregular updates from other disciplines in Autodesk Construction Cloud (ACC) caused misalignment during coordination.
- Areas were constructed differently than shown in drawings, but no formal site communication was provided.
- Phase mismatches and lack of centralized issue tracking made sheet generation error-prone and slow.
- Deliverables needed to align with ISO 19650 and a strict BIM Execution Plan, which was beyond the contractor's in-house capacity.